Kernaussage: The Court can reject a new line of arguments pursuant to R.

2025-07-30 - LD Düsseldorf - Headwater Research v. Samsung - UPC_CFI_26/2024
Eine Entscheidung, mehrere Aktenzeichen

Das Gericht hat diese Verfahren zusammen entschieden und dasselbe Dokument in jedem davon eingestellt. Jeder Eintrag unten ist ein eigener vollwertiger Registereintrag.

🏛️Court of First Instance - Düsseldorf (DE) Local Division• Proceeding Decision
📅2025-07-30
🔢UPC_CFI_26/2024
Parteien & Vertreter
Kläger / Berufungsführer
Headwater Research LLC
Michael SCHNEIDER
Beklagter / Berufungsbeklagter
Samsung Electronics GmbH
Samsung Electronics France, S.A.S.
Samsung Electronics Benelux B.V.
Samsung Electronics Co. Ltd.
Martin KÖHLER
📋ORD_69354/2024
⚖️Infringement Action
🌐English

The Court can reject a new line of arguments pursuant to R. 9.2 RoP in a case where the issue has been raised from the outset and the new argument is based on completely different passages of a lengthy document. Neither the Court nor the other party may be forced to deal with it from scratch. This undermines the concept of the front-loaded procedure established by the Rules of Procedure.

The Düsseldorf Local Division granted a counterclaim for revocation due to added subject-matter and rejected the application to amend the patent as none of the auxiliary requests cured the objection of added matter. Consequently, the Court dismissed the infringement action. The Court had disregarded arguments which were only brought forwarding in the oral hearing, stating that this was against the UPC's principle of front-loaded proceedings and that the Defendants and the Court could not be forced to deal with it from scratch.
Stichwörter
R. 9.2 RoP, added-matter

Nichtigkeitsgründe

Art. 138 EPC
1 Grund
Added Matter
Art. 123(2) EPC · Art. 138(1)(c) EPC
Patent invalid (this ground)
“Application vs network service usage activity is material distinction. 26 auxiliary requests failed.”
Feststellungen aus Sicht des Patentinhabers bezeichnet. Quelle: KI-Klassifikation (AI)

Entscheidung teilen

Weitere Navigation
Entscheidungen
Rechtstexte
Analysen

Zu Sammlung hinzufügen

0 Einträge hinzufügen zu:

Anmeldung

Registrieren